Toggle navigation
|
Inbox
View Profile
Log Out
FM.MT.05.01
SURAT PERINTAH KERJA ( WORK ORDER )
WORKORDERNO
WORKCENTER
PRIORITY
TGLDIKERJAKAN
DURASIPEKERJAAN
EQUIPNO
JUMLAHORANG
EQUIPDESC
DESKRIPSI KERJA
1. Preventive Connection, Cleaning, Coil Magnetic Sensor dan Limit Switch Preventive Connection, Cleaning, Tightening Motor dan Fan Cantiliver Machine
MATERIAL
TOOLS
PROCEDURE :
1. Preventive Connection, Cleaning, Coil Magnetic Sensor dan Limit Switch Preventive Connection, Cleaning, Tightening Motor dan Fan Cantiliver Machine
TglMulai
TglSelesai
TotalJam
Status
NamaPekerja1
NamaPekerja3
NamaPekerja2
NamaPekerja4
Comment :
1. Preventive Connection, Cleaning, Coil Magnetic Sensor dan Limit Switch Preventive Connection, Cleaning, Tightening Motor dan Fan Cantiliver Machine (DONE)
Download
Back to List