FM.MT.05.01
SURAT PERINTAH KERJA ( WORK ORDER )
WORKORDERNO
WORKCENTER
PRIORITY
TGLDIKERJAKAN
DURASIPEKERJAAN
EQUIPNO
JUMLAHORANG
EQUIPDESC
DESKRIPSI KERJA
Installasi Pipa untuk sirkulasi cat warna putih di area U-Wrap Coater
MATERIAL
TOOLS
Double nepel SS304 3/4" (2), Reducer SS304 1/2"X3/4" (2), Double nepel SS304 1/2" (4), Nepel Hose SS304 3/4" (12), Elbow 90Deg SS304 3/4" (8), Pipe Sch40 ss304 3/4" (2), Hose Chemical 3/4" (4), Ball Valve SS304 3/4" (4), Water Mur ss304 3/4" (4), FILTER CATRIDGE SS304 10" (1), Support Pipe (1), Clamp Pipe 3/4" (1)
Travo las, kedok las, sarung tangan las, faceshield, palu (1), Pipe threading machine (1), Gerinda tangan, chipping hammer, measuring tape (1)
PROCEDURE :
Instruksi Safety : 1. Gunakan PPE level 1 dan Level 2 2. Pastikan area kerja aman dan lakukan prosedur isolasi 3. Tanya supervisor untuk kondisi darurat, panggil petugas medical untuk perawatan Aspek Lingkungan: 1. Buang sampah dan limbah B3 di TPS Instruksi Pekerjaan : 1. Pelajari dan pahami gambar kerja yang telah dibagikan 2. Persiapkan material, alat kerja, dan alat bantu kerja 4. Potong material pipa sesuai ukuran digambar kerja 5. Lakukan fitting pada pipa dengan material lain seperti elbow dan ball valve 6. Install pipa sesuai dengan gambar kerja berikut dengan support pipanya 7. Lakukan finishing dan 5R
TglMulai
TglSelesai
TotalJam
Status
NamaPekerja1
NamaPekerja3
NamaPekerja2
NamaPekerja4
Comment :
- Pekerjaan sudah selesai, Kekurangan reducer dan double nipple 1/2 untuk selang ke pompa