FM.MT.05.00
SURAT PERINTAH KERJA
WORKCENTER
PRIORITY
WORKORDERNO
TGLDIKERJAKAN
EQUIPNO
DURASIPEKERJAAN
EQUIPDESC
JUMLAHORANG
DeskripsiKerja
INJECT CHLORINE STP
Material
Prima 517 (chemical cooling) (1)
Tools
Trolley (1)
Procedure
Safety : Gunakan APD chemical handling sarung tangan dam kacamata Environment Standar baku mutu chlorine 1 mg/L Langkah kerja : 1. Siapkan chemical chlorine 25 kg/jerigen 2. Setingan pump dosing chemical 10 %
TglMulai
TglSelesai
TotalJam
Status
OPEN
OnProgress
Inspection
COMPLETED
NamaPekerja1
NamaPekerja3
NamaPekerja2
NamaPekerja4
Comment
Upload File
LINE CONDITION
Deskripsi
Tanggal Dibutuhkan